Installation of the Bin Sorter is moving along...

All components of the new bin sorter have been delivered and staged for installation. This completes phase 1 of the project (photos below)







 

As of mid November, phase 2 is nearing completion with the construction of the Piche bin sorter, stacker and Samuel's strapping system (photos below.)


The next phase of the process will include the Comact trimmer and the grading scanner. The overall projected timeframe of completion is scheduled for Mid January 2023.